Wenzhou Pingyang – National Highway G228 Project

Time:2023-06-30 16:46:41    Number of views:9

Project Name: Civil Works Section II of the G228 National Highway (Pingyang Yuyang to Aojiang Segment)


Total Contract Value: RMB 228,196,969


Scope of Work:

Subgrade construction, bridgeworks, and asphalt pavement


Completion Date: September 28, 2021



Project Details:


  • Mainline Length: 3.33 km

  • Number of Bridges: 7

  • Road Realignment: 1.258 km total


    • 685 m realignment at K6+459 (left side)

    • 573 m realignment at Wan’ao

  • Road Classification: First-class highway standard




Major Quantities:



1. 

Subgrade Works:


  • Earth excavation: 252,496 m³

  • Static rock blasting: 290,227 m³

  • Earth-rock mixed backfill: 155,546 m³

  • Cement mixing piles (d = 0.5 m): 390,982 m

  • M7.5 mortared stone retaining wall: 12,587 m³

  • Retaining wall foundations (C25 concrete): 672 m³

  • C20 rubble concrete spread footings: 4,257 m³

  • Cantilever and counterfort retaining walls (C25 concrete): 4,196 m³



2. 

Bridge Works:


  • Muxiang Bridge Left Span (ZK6+459.0): 1 span × 20 m

  • Muxiang Bridge Right Span (YK6+560.0): 8 spans × 30 m

  • Yantou Bridge (K8+429.0): 3 spans × 20 m

  • Fengshan Bridge Left No.1 (K8+966.0): 8 spans × 20 m

  • Fengshan Bridge Left No.2 (K9+381.5):

    Superstructure: Prestressed concrete T-beams + cast-in-place variable-section prestressed continuous concrete box girder

    Span configuration: 4×30 + (31 + 2×55 + 40) + 7×30

  • Fengshan Bridge Right (K9+261.5):

    Superstructure: Prestressed concrete T-beams + cast-in-place variable-section prestressed continuous concrete box girder

    Span configuration: 12×20 + 3×30 + (40 + 2×55 + 31) + 8×30

  • Lower Fengshan Bridge Left (K14+323.0): 5 spans × 13 m



3. 

Asphalt Pavement:


  • Asphalt concrete pavement area: 25,743.59 m²