Wenzhou Pingyang – National Highway G228 Project
Time:2023-06-30 16:46:41 Number of views:9
Project Name: Civil Works Section II of the G228 National Highway (Pingyang Yuyang to Aojiang Segment)
Total Contract Value: RMB 228,196,969
Scope of Work:
Subgrade construction, bridgeworks, and asphalt pavement
Completion Date: September 28, 2021
Project Details:
Mainline Length: 3.33 km
Number of Bridges: 7
Road Realignment: 1.258 km total
685 m realignment at K6+459 (left side)
573 m realignment at Wan’ao
Road Classification: First-class highway standard
Major Quantities:
1.
Subgrade Works:
Earth excavation: 252,496 m³
Static rock blasting: 290,227 m³
Earth-rock mixed backfill: 155,546 m³
Cement mixing piles (d = 0.5 m): 390,982 m
M7.5 mortared stone retaining wall: 12,587 m³
Retaining wall foundations (C25 concrete): 672 m³
C20 rubble concrete spread footings: 4,257 m³
Cantilever and counterfort retaining walls (C25 concrete): 4,196 m³
2.
Bridge Works:
Muxiang Bridge Left Span (ZK6+459.0): 1 span × 20 m
Muxiang Bridge Right Span (YK6+560.0): 8 spans × 30 m
Yantou Bridge (K8+429.0): 3 spans × 20 m
Fengshan Bridge Left No.1 (K8+966.0): 8 spans × 20 m
Fengshan Bridge Left No.2 (K9+381.5):
Superstructure: Prestressed concrete T-beams + cast-in-place variable-section prestressed continuous concrete box girder
Span configuration: 4×30 + (31 + 2×55 + 40) + 7×30
Fengshan Bridge Right (K9+261.5):
Superstructure: Prestressed concrete T-beams + cast-in-place variable-section prestressed continuous concrete box girder
Span configuration: 12×20 + 3×30 + (40 + 2×55 + 31) + 8×30
Lower Fengshan Bridge Left (K14+323.0): 5 spans × 13 m
3.
Asphalt Pavement:
Asphalt concrete pavement area: 25,743.59 m²